H1 > Fast Navigator > Tracker > Upgrade > Pictures |
103, 12.2.02
108, 14.7.02
112, 13.1.03
Tunnel work.
113, 13.1.03
Concrete shielding removal. SpaCal removal,
114, 6.3.03
SpaCal, opening of forward toroid.
115, 10.3.03
BPC removal.
116, 10.-18.3.03
New beam pipe in quadrupoles in NR.
Burnt C5B collimator.
GO magnet raising.
Tunnel NL before VFPS cold bypass installation.
117, 18.3.03
Tracker hole after CST installation,
FPS fiber detectors.
118, 20.3.03
VFPS bypass.
119, 20.3.03
FST removal.
120, 20.3.03
VFPS bypass.
BST
BST installation.
122, 10.6.03
New C5B collimator with integrated getter pump,
BST installation.
123, 10.6.03
124, 13.6.03
BPC.
125, 13.6.03
GO magnet.
126, 17.6.03
New C5B collimator with integrated getter pump installed.
127, 17.6.03
New C5B collimator with integrated getter pump installed.
128, 19.6.03
BPC installed.
129, 2.7.03
SpaCal installed, BU NR repair.
130, 3.7.03
Repair of broken BU magnet, NR.
Klystrons on 4th floor.
132, 30.7.03
BTS.
134, 2003
Etag 40.
137, Dec 2003
H1 shielding.
138, June 2004
Leak NR11m.
139, 11.7.2004
New FPS stations.
140, 2.8.2004
BTS 6m.
142, 23.8.2004
GI2 magnet and beam pipe.
143, 27.8.2004
burned GI2 beam pipe, CIP repair
144, 1.9.2004
ABS4 removed, BSToF
145, 2.9.2004
CIP repair
146, 8.9.2004
Lumi veto and Be filter, FPS.
147, 13.9.2004
new BSToF
148, 13.9.2004
BSToF insertion
149, 23.9.2004
renewed FPS stations
150, 9.12.2004
maintenance day, CDA, N2 shield
152, Dez 2004
Magnets NR, ET 40
155, 29.6.2006
Burned GI beam pipe